PROPOSED HOTEL
AT :ELECTRONIC CITY ~BANGALORE |
|
|
|
THE STATISTICS |
SIZE : 1.5 Acres ~ 6,075 sqm ~ 65,350 sft.
FRONTAGE : 80m ~ 275 ft.
SHAPE : ALMOST RECTANGULAR.
FACING : NORTH.
LOCATION : ELECTRONICS CITY PH I, BANGALORE.
LANDMARKS: opp STPI, in close proximity with GE Capital, HP, Wipro, Infosys etc. |
|
|
|
THE LEGALITIES |
FREE HOLD PROPERTY.
REGISTRATION / KHATA IN NAME OF OWNERS.
PLANS APPROVED BY KIADB
PLANS APPROVED BY FIRE DEPT
PLANS APPROVED BY CIVIL AVIATION
CONSTRUCTION IN FULL SWING |
|
|
APPROXIMATE BUILT UP AREAS |
TOTAL BUILT UP AREA: 13075 SQM*
Ground Floor : 1352sqm [Reception, Restaurant, CoffeeShop]
First Floor : 1230sqm [Bar, Speciality Restaurant, Terrace Garden, Business Center]
Second Floor : 1080sqm [12 keys]
Third Floor : 1080sqm [16 keys]
Fourth Floor : 1080sqm [16 keys]
Fifth Floor : 1120sqm [16 keys]
Sixth Floor : 1120sqm [16 keys]
Seventh Floor : 1043sqm [16 keys]
Eighth Floor : 277.5sqm [4 keys]
Ninth Floor : 277.5sqm [4 keys]
Upper Basement : 1645sqm [Health Club, Squash Court, Pool, Retail]]
Lower Basement : 1770sqm [Parking] |
|
|
|
Current Status of Works |
Civil Structure –Complete
Lifts –4 of 6 lifts are erected. Material at site
Central Electrical Panel Room –Complete
Electrical Cabling –Complete till each floor
Sewerage Treatment Plant –Complete
Generators –2 * 500kva Gensetsinstalled
Glazing and front elevation –90% complete
Swimming Pool –Structure complete. Pumps to be installed.
Plumbing for Fire –Complete
Plumbing for Hot/Cold and Sewerage –Complete till bathroom. |
|
|
|
Works to be done |
|
Central Air-conditioning including Chillers etc.
Transformers (1200kva)
Civil –Plastering of interiors
Room -Fittings and Furniture to be installed for all rooms
Restaurants( Speciality, Coffee shop, terrace and sports bar) to be completed with kitchen equipment.
Banquet hall and Meeting rooms to be completed
Lobby Area to be finished
Permanent Power to be requested from KEB/BESCOM
Water and sewerage connection to be requested from BWSSB/ELCIA |
|
|
|
|
|
|